Cameroon textile programme / Section 08 · Communications calendar

Twelve months in three phases.
Close the year with measured evidence.

Pre-launch (M1 to M3) tells the SODECOTON provenance story and briefs founding buyers. Launch (M4 to M6) opens retail, e-commerce and institutional outreach. The sustained phase (M7 to M12) turns logged quality into tenders, distributors and a measured Year-1 report.

Operate the twelve-month ringProcedural visualisation. Schematic, not a facility.

01 / One programme read twice · Months 1 to 12

Communications move in lockstep with the factory, so promises never outrun evidence.

Section 8 of the Feasibility Study paces the year in seven campaign windows. The white thread inside the ring is the proof ply: each message is punched only where the factory already holds its evidence.

M1M2M3M4M5M6M7M8M9M10M11M12WINDOWM1-M2PRE-LAUNCHM3PRE-LAUNCHM4LAUNCHM5-M6LAUNCHM7-M8SUSTAINEDM9-M10SUSTAINEDM11-M12SUSTAINED
M1 at the top, clockwise. Ochre pre-launch, sage launch, indigo sustained; a hole for each live channel-month.

Window 1 of 7 · Pre-launch

M1 to M2

SaysBrand, sustainability story, trade teasers

  • PR
  • Social
  • Trade press
Rests on

>220,000

northern growers supported by SODECOTON across nine ginning plants
≈US$100m a year injected into rural communities

Window 2 of 7 · Pre-launch

M3

SaysFounding-buyer and distributor briefings

  • Direct
  • Events
Rests on

>90%

computer-vision defect accuracy, against 60 to 70% for manual inspection

Window 3 of 7 · Launch

M4

SaysFirst collection, provenance campaign

  • Social
  • Retail
  • E-commerce
Rests on

+13.41%

a year, Cameroon apparel e-commerce revenue
User penetration 18.0% (2023) to 22.7% (2027)

Window 4 of 7 · Launch

M5 to M6

SaysRetail activation, institutional outreach

  • Retail
  • Direct
Rests on

Douala · Yaoundé

retail floors and the first B2B uniform-buyer meetings

Window 5 of 7 · Sustained

M7 to M8

SaysRepeat-order push, uniform tenders

  • Direct
  • Tender
  • E-commerce
Rests on

6 months

of logged on-time-in-full and first-pass yield behind the first tender bids

Window 6 of 7 · Sustained

M9 to M10

SaysRegional distributor onboarding

  • Trade
  • Distributor
Rests on

2 blocs

CEMAC and CEEAC, named for distributor onboarding

Window 7 of 7 · Sustained

M11 to M12

SaysAnniversary, impact report, scale story

  • PR
  • Social
  • Trade press
Rests on

6 ratios

metered in the Month-12 report, each with a unit and a denominator
M1 to M2 · Pre-launch

02 / The year tape, laid flat

Seven campaign windows allocate focus and channels from Month 1 to Month 12.

Each window punches only the channels its commercial objective needs. Switch a channel off at its track label, or filter by phase.

31channel-months scheduled

All windows: the busiest months carry 3 channels

Window 1 of 7 · M1 to M2 · Pre-launch

Brand, sustainability story, trade teasers

PR, Social, Trade press. Establishes the 95/5 local-processing gap and the traceable SODECOTON cotton origin (more than 220,000 growers).

Window 2 of 7 · M3 · Pre-launch

Founding-buyer and distributor briefings

Direct, Events. Presents physical and digital samples, the quality specification (above 90 percent computer-vision accuracy) and delivery terms before garments ship.

Window 3 of 7 · M4 · Launch

First collection, provenance campaign

Social, Retail, E-commerce. Targets Priority 1 traditional and urban ready-to-wear across retail and the online channel growing at 13.41 percent a year.

Window 4 of 7 · M5 to M6 · Launch

Retail activation, institutional outreach

Retail, Direct. Drives domestic sell-through in Douala and Yaoundé while opening B2B uniform buyer meetings.

Window 5 of 7 · M7 to M8 · Sustained

Repeat-order push, uniform tenders

Direct, Tender, E-commerce. Uses six months of logged on-time-in-full and first-pass yield data from the performance-management system to bid on institutional contracts.

Window 6 of 7 · M9 to M10 · Sustained

Regional distributor onboarding

Trade, Distributor. Appoints wholesale partners across the CEMAC and CEEAC regional bloc once domestic fulfilment is stable.

Window 7 of 7 · M11 to M12 · Sustained

Anniversary, impact report, scale story

PR, Social, Trade press. Publishes metered Year-1 water, dye, energy and waste figures from the system sustainability log.

Schedule arithmetic from the Section 8 table: it counts scheduled channels per month, not spend, reach or results. Open the full Comms Planner

Channels in play: switch a channel off to plug its holes
WindowPhaseCampaign focusChannels and operational link
M1 to M2Pre-launchBrand, sustainability story, trade teasersPR, Social, Trade press. Establishes the 95/5 local-processing gap and the traceable SODECOTON cotton origin (more than 220,000 growers).
M3Pre-launchFounding-buyer and distributor briefingsDirect, Events. Presents physical and digital samples, the quality specification (above 90 percent computer-vision accuracy) and delivery terms before garments ship.
M4LaunchFirst collection, provenance campaignSocial, Retail, E-commerce. Targets Priority 1 traditional and urban ready-to-wear across retail and the online channel growing at 13.41 percent a year.
M5 to M6LaunchRetail activation, institutional outreachRetail, Direct. Drives domestic sell-through in Douala and Yaoundé while opening B2B uniform buyer meetings.
M7 to M8SustainedRepeat-order push, uniform tendersDirect, Tender, E-commerce. Uses six months of logged on-time-in-full and first-pass yield data from the performance-management system to bid on institutional contracts.
M9 to M10SustainedRegional distributor onboardingTrade, Distributor. Appoints wholesale partners across the CEMAC and CEEAC regional bloc once domestic fulfilment is stable.
M11 to M12SustainedAnniversary, impact report, scale storyPR, Social, Trade press. Publishes metered Year-1 water, dye, energy and waste figures from the system sustainability log.

03 / Months 1 to 6 · Pre-launch and launch

Lay the cotton thread before a single garment leaves the finishing room.

5%of cotton fibre processed locally today

>90%vision accuracy, 40+ defect types

+13.41%a year, apparel e-commerce

Douala · Yaoundéretail floors, then the first uniform buyers

Step 01 · M1 and M2 · Origin

Tell the origin story before there is a product.

Cameroon grows more than 300,000 tonnes of seed cotton a year (314,455 tonnes in 2023, about 340,000 in 2024) across more than 220,000 northern growers , yet about 95 percent of the fibre leaves raw . Each thread is one percent: five stay. PR and trade press open on this gap.
State of the thread
The 2030 state is the SND30 target, not a result .

Step 02 · M3 · Briefings

Brief founding buyers with the inspection standard, not a promise.

The five local threads ply into one cotton thread: northern growers, SODECOTON's nine ginning plants , the finishing room, the founding buyers. Their briefing shows the garment beside the standard: computer vision above 90 percent accuracy across more than 40 defect types, against 60 to 70 percent for manual inspection .

Step 03 · M4 · First collection

Release the first collection with its provenance attached.

The online channel the campaign reaches grows 13.41 percent a year, from US$20.32m (2023) to US$33.61m (2027) . Each care label resolves back through six lots. Walk them, or open the Trace-a-garment simulator.

Link 1 of 6 · Gin lot. The upstream boundary of the record. A recorded gin lot does not identify a farm or authenticate the fibre.

Link 2 of 6 · Lint bale. Carries the gin-lot reference as its parent, with an accountable operator, a location and an event time.

Link 3 of 6 · Yarn lot. Names the bales it consumed. A blend would need a richer record than a single parent reference.

Link 4 of 6 · Fabric roll. Points to its yarn lot. A missing yarn reference at this link is where a trace would stop.

Link 5 of 6 · Cut bundle. Splits a roll into bundles. Each bundle keeps the roll reference, so the chain stays one line.

Link 6 of 6 · Garment. The care-label serial a Month-4 buyer can read. It resolves back through the five links above it.

Illustrative single-parent model, not proof of physical origin.

Step 04 · M5 and M6 · Retail and B2B

Move from awareness to the shop floor and the first uniform buyers.

Retail activation in Douala and Yaoundé drives domestic sell-through, while the first B2B meetings with institutional and uniform buyers prepare the tenders of Months 7 and 8. The ochre branch leaves the stage toward them, and the tape advances to Month 7: the second half of the year starts there.

04 / Month 12 · The proof card

The Year-1 report prints metered ratios, not marketing adjectives.

Sections 5 and 8 of the Feasibility Study tie each sustainability claim to its measurement; Deliverable 2 specifies the logs the Month-12 report is compiled from.

6 ratiosSix ratios, each with a unit and a denominatorPoint at a lamp to light its bars and read what it measures.The bar field is a procedural illustration, not measured data.
6 links
Gin lot to garment, with a record at each link
Each garment resolves back through its cut bundle, fabric roll, yarn lot and bale to a gin lot.The bar field is a procedural illustration, not measured data.
Water ÷ garments
Metered water per accepted garment
Metered water, divided by accepted garments, logged from the first shift.The bar field is a procedural illustration, not measured data.
kWh ÷ garments
Utility-meter kilowatt-hours per accepted garment
Kilowatt-hours from the utility meters, divided by accepted garments.The bar field is a procedural illustration, not measured data.
Waste ÷ cut
Cutting-room waste as a ratio from the daily line log
Waste in the cutting room, reported as a ratio from the daily line log.The bar field is a procedural illustration, not measured data.
XAF 43,969
a month, the SMIG floor the wage band stays above
Wage band progression, held above the SMIG floor of XAF 43,969 a month.The bar field is a procedural illustration, not measured data.
>90%
computer-vision defect-detection accuracy
Computer-vision defect detection above 90 percent accuracy, against 60 to 70 percent for manual inspection.The bar field is a procedural illustration, not measured data.

M12 frame, enlarged6 proof lamps

05 / Months 7 to 12 · Sustained commercial conversion

The second half of the year converts attention into repeat orders, tenders and regional distribution.

Q3 · M7 and M8 · Repeat and tenders

Turn six months of quality logs into B2B uniform contracts.

6 monthsof logged on-time-in-full and first-pass yield behind the first tender bid

A consumer launch creates awareness; repeat orders and institutional contracts fill the line. Direct sales and tender teams bid for corporate workwear and school uniforms on audited first-pass yield and on-time-in-full records, while e-commerce runs repeat-buyer campaigns.

Open the performance-management system

Q3 to Q4 · M9 and M10 · Regional bloc

Onboard wholesale distributors across CEMAC and CEEAC.

2 blocsnamed for distributor onboarding, CEMAC and CEEAC

With Douala and Yaoundé replenishment running smoothly, trade outreach appoints regional distributors to carry traditional wear and ready-to-wear across Central Africa. The Distributors bar spans the fold. The bloc rings are schematic outlines: no market size is claimed.

Open the market-access mapper

Q4 · M11 and M12 · Impact and scale

Publish the Year-1 measured impact report across all 12 months.

6 ratiosmetered in the Month-12 report · 12 of 12 months · 31 channel-months · 7 windows

The launch year closes with a sustainability and quality report compiled from the shop-floor system of record. Unfolded, the four quarters are one tape again: the Phase 2 line-expansion story starts from this record of what the year measured, not from a forecast.

Open the footprint calculator

06 / The release desk · Month 12 · Ring and tape re-assembled

Run the calendar in three phases, keep provenance as the spine, and close Year 1 with measured evidence.

Start the year with a traceable cotton thread; finish it with a measured impact ledger.

M1M2M3M4M5M6M7M8M9M10M11M12WINDOWM1-M2PRE-LAUNCHM3PRE-LAUNCHM4LAUNCHM5-M6LAUNCHM7-M8SUSTAINEDM9-M10SUSTAINEDM11-M12SUSTAINED

12-MONTH RING & PROOF THREAD · ALL 12 LIT

Choose a claim to clear on the year tape

7 of 7 claims cleared · head at M12

Held until M1

Provenance story · M1 to M2

Before M1 this message would be an adjective without a batch denominator, and adjectives without batch denominators collapse under buyer due diligence.

Cleared from M1

Provenance story · M1 to M2

>220,000 northern growers supported by SODECOTON across nine ginning plants
Open the Trace-a-garment simulator

Held until M3

Buyer briefings · M3

Before M3 this message would be an adjective without a batch denominator, and adjectives without batch denominators collapse under buyer due diligence.

Cleared from M3

Buyer briefings · M3

>90% computer-vision defect accuracy, against 60 to 70% for manual inspection
Open the performance-management system

Held until M4

First collection · M4

Before M4 this message would be an adjective without a batch denominator, and adjectives without batch denominators collapse under buyer due diligence.

Cleared from M4

First collection · M4

+13.41% a year, Cameroon apparel e-commerce revenue
Open the Comms Planner

Held until M5

Retail floors · M5 to M6

Before M5 this message would be an adjective without a batch denominator, and adjectives without batch denominators collapse under buyer due diligence.

Cleared from M5

Retail floors · M5 to M6

Douala · Yaoundé retail floors and the first B2B uniform-buyer meetings
Open the Comms Planner

Held until M7

Repeat and tenders · M7 to M8

Before M7 this message would be an adjective without a batch denominator, and adjectives without batch denominators collapse under buyer due diligence.

Cleared from M7

Repeat and tenders · M7 to M8

6 months of logged on-time-in-full and first-pass yield behind the first tender bids
Open the performance-management system

Held until M9

Regional bloc · M9 to M10

Before M9 this message would be an adjective without a batch denominator, and adjectives without batch denominators collapse under buyer due diligence.

Cleared from M9

Regional bloc · M9 to M10

2 blocs CEMAC and CEEAC, named for distributor onboarding
Open the market-access mapper

Held until M11

Impact report · M11 to M12

Before M11 this message would be an adjective without a batch denominator, and adjectives without batch denominators collapse under buyer due diligence.

Cleared from M11

The measured impact ledger is open.

  • Bale-to-garment lot lineage
  • Metered water per accepted garment
  • Metered kilowatt-hours per accepted garment
  • Cutting-room waste ratio
  • Wage band progression above the SMIG floor
  • Computer-vision accuracy above 90 percent
Open the footprint calculator
Evidence and limits. The calendar reproduces Section 8 of GFT's Cameroon textile feasibility study (prepared 31 January 2024; sources refreshed 2026). The clearance rule is that schedule read as a rule: a schematic, not a compliance system. Not investment, legal or tax advice.