TAKT 1.40 MINS11.25S21.30S30.55S41.15S51.35S61.30S71.25S80.50
300

GFT instruments / Line-balancing studio

Balance the work.
Then staff the line.

The illustrative T-shirt route needs eight stations for 300 garments in 420 net minutes. Start with six operators, edit the work, and see what constrains the line.

Operate the instrumentProcedural visualisation. Schematic, not a facility.

01 / The bench

Where is the bottleneck, and how many operators fix it?

Illustrative T-shirt route

No sourced programme SMVs were supplied. These teaching inputs are not a factory benchmark. Every result is derived from the inputs below, and the loom in the opening follows them.

Set the shift boundary.
Choose the routing assumption.

Flexible work ignores predecessor links. Use it to explore a ceiling, then validate the physical route. Each station still has one operator.

Candidate staffing

8operators required

2 additional operators for this assignment

Takt1.40 min
Balance efficiency80.1%
Labour lower bound7 people
Bottleneck cycle1.35 min

This heuristic uses 8 stations, 2 more operators than the 6 entered. The aggregate lower bound is 7; precedence and task sizes explain why a workable assignment can need more. Station 5 sets the 1.35 min bottleneck cycle. Validate machines, skills and handling before moving work.

Yamazumi / workload by station

The highest stack sets the pace.

Work 8.65 minIdle at takt 2.55 minOverload 0.00 min

Illustrative station balanceThis heuristic uses 8 stations, 2 more operators than the 6 entered. The aggregate lower bound is 7; precedence and task sizes explain why a workable assignment can need more. Station 5 sets the 1.35 min bottleneck cycle. Validate machines, skills and handling before moving work.0.000.430.851.281.71MIN / GARMENT01 Join shoulders: 0.65 min0105 Hem sleeves: 0.60 min051.25S102 Prepare neck rib: 0.45 min0203 Attach neck rib: 0.85 min031.30S204 Topstitch neck: 0.55 min040.55S306 Attach sleeves: 1.15 min061.15S407 Close side seams: 1.35 min071.35S508 Hem body: 0.95 min0809 Attach label: 0.35 min091.30S610 Trim threads: 0.55 min1011 Inspect: 0.70 min111.25S712 Fold: 0.50 min120.50S8TAKT 1.40 MIN

Editing: S5 · 07 Close side seams (1.35 min bottleneck against 1.40 min takt). Hover any block to inspect.

02 / Operation bulletin

Make every minute editable.

EditingS5 · 07 Close side seams (1.35 min)

01 Join shoulders: 0.65 min, station S10105 Hem sleeves: 0.60 min, station S1051.25S102 Prepare neck rib: 0.45 min, station S20203 Attach neck rib: 0.85 min, station S2031.30S204 Topstitch neck: 0.55 min, station S3040.55S306 Attach sleeves: 1.15 min, station S4061.15S407 Close side seams: 1.35 min, station S5071.35S508 Hem body: 0.95 min, station S60809 Attach label: 0.35 min, station S6091.30S610 Trim threads: 0.55 min, station S71011 Inspect: 0.70 min, station S7111.25S712 Fold: 0.50 min, station S8120.50S8TAKT 1.40 MIN
Work
8.65 min
Stations
8
Takt
1.40 min
Efficiency
80.1%
  • S11.25 min
  • S21.30 min
  • S30.55 min
  • S41.15 min
  • S51.35 min
  • S61.30 min
  • S71.25 min
  • S80.50 min

SMV means standard minutes per garment. Predecessors are comma-separated IDs that must be completed first. IDs stay fixed. Remove dependent links before removing an operation. The supported editor limit is 32 operations. Each thread is drawn to its SMV against the takt mark.

01
02
03
04
05
06
07
08
09
10
11
12

Live read-out · active focus

Editing: S5 · 07 Close side seams1.35 min on station S5 (bottleneck cycle 1.35 min against 1.40 min takt). 12 operations, 8.65 min total work.

03 / Method: keep the denominator visible

The arithmetic runs in five steps.

010203040506070809101112STANDARD WORK, IN ROUTE ORDER1t2t3t4t5t6t1234567CYCLE 1.35 MINS11.25S21.30S30.55S41.15S51.35S61.30S71.25S80.50TAKT 1.40 MIN

Illustrative route; blocks keep their operation colours. Do not combine observed seconds for one task with unadjusted standard minutes for another.

01 / Denominator

Name the denominator first.

The shift boundary is net available production time for the whole line. Enter demand for that same period. SMV is the standard work content of an operation, in minutes per garment. Keep one allowance convention across the bulletin.

W = sum of SMVs = 8.65 min

02 / Takt

Takt is the time the line can spend on one garment.

Divide net production minutes by the garments due in that window. Every station must finish inside this time, or the target slips. The ribbon is cut at each takt: the cuts count how many takts of work one garment holds.

t = 420 ÷ 300 = 1.40 min

03 / Ceiling

A lower bound is not an assignment.

Round the work up to whole takts and you have the fewest stations arithmetic allows. It is a ceiling, nothing more: it ignores predecessors and task sizes, so a workable assignment can need more people.

Nmin = ceiling(8.65 ÷ 1.40) = 7

04 / Assignment

The largest candidate fills each station.

Tasks are sorted by descending SMV. Each station takes the largest unassigned task that fits the remaining takt and whose predecessors are placed. When nothing fits, a new station opens. It is a reproducible heuristic; it does not prove the smallest station count.

Stations = 8

05 / Efficiency

Read efficiency at the bottleneck, not at takt.

Balance efficiency divides the work by stations times the bottleneck cycle, so it describes how work is spread, not whether the target is achievable. Idle sums gaps below takt; overload sums excess above it. A task above takt gets a diagnostic station and no staffing answer.

E = 8.65 ÷ (8 × 1.35) = 80.1%

04 / Assignment and idle-time ledger

Every minute of idle time sits on a named station.

Sort the cloth by

Minutes are per garment. Woven blocks run to each station's load; the hatched warp runs on to the dashed takt mark. A bullet identifies a bottleneck. An overloaded station means the target cannot be met under the indivisible-task assumption.

Assignment and idle-time ledger by station
StationOperations in execution orderCloth against taktLoad (min)Idle (min)Overload (min)
S101 Join shoulders
05 Hem sleeves
0105
1.250.150.00
S202 Prepare neck rib
03 Attach neck rib
0203
1.300.100.00
S304 Topstitch neck
04
0.550.850.00
S406 Attach sleeves
06
1.150.250.00
S5 •07 Close side seams
07
1.350.050.00
S608 Hem body
09 Attach label
0809
1.300.100.00
S710 Trim threads
11 Inspect
1011
1.250.150.00
S812 Fold
12
0.500.900.00

Reconciliation: work + idle at takt = stations × takt + overload, even when the target is infeasible8.65 work + 2.55 idle = 8 stations × 1.40 takt + 0.00 overload

05 / A and B, one scale

Keep the baseline while testing a change.

A is the illustrative default, saved for you, drawn as an outline. B is the current inputs, woven. Drag the divider to wipe between them. The saved inputs remain fixed in this tab, the share link contains B, and calculations run locally in the browser.

S1S2S3S4S5S6S7S8
S1S2S3S4S5S6S7S8

A illustrative default, pre-saved: 8 stations, takt 1.40 minB current inputs: 8 stations, takt 1.40 min

  • Stations8 → 8no change
  • Takt1.40 min → 1.40 minno change
  • Balance efficiency80.1% → 80.1%no change
Show the full decision table
0 stations; 0.00 min change in bottleneck cycle. A is the saved snapshot; B is current.
Decision measureSaved ACurrent B
Target garments300300
Net minutes420420
Available operators66
Routingprecedenceprecedence
Total work (min)8.658.65
Takt (min)1.401.40
Feasible at targetYesYes
Heuristic stations88
Additional operators22
Bottleneck cycle (min)1.351.35
Balance efficiency80.1%80.1%
300

06 / Interlude: follow the loss beyond the balance

Idle at takt is the first loss, not the last.

11.20 station-minutes per garment: 8.65 woven, 2.55 hanging as slack, 0.00 overload. Availability, performance and quality losses are not modelled here.

S1S2S3S4S5S6S7S8overload 0.00Availabilitynot modelledPerformancenot modelledQualitynot modelled
S11.25 woven · 0.15 slackS21.30 woven · 0.10 slackS30.55 woven · 0.85 slackS41.15 woven · 0.25 slackS51.35 woven · 0.05 slackS61.30 woven · 0.10 slackS71.25 woven · 0.15 slackS80.50 woven · 0.90 slackoverload 0.00Availabilitynot modelledPerformancenot modelledQualitynot modelled

Idle at takt -2.55 min Gap below the takt guide: the slack loops, one per station with idle time.

Use the OEE instrument ↗ to separate availability, performance and quality within a shift. Labour cost and ramp planning are related decisions; this studio does not calculate wages, training duration or investment returns.

07 / Read the candidate responsibly

Prove the constraint before changing the crew.

Choose what to inspect

Station S5 sets the cycle at 1.35 min.

8 required · 6 available · 2 additional. Lower bound 7.

Ceiling if every station is staffed: 311 garments per shift.

8.65 work + 2.55 idle = 8 stations × 1.40 takt + 0.00 overload

OVERLOAD 0.00 MINS1S2S3S4S5S6S7S8TAKT 1.40CYCLE 1.35 MIN07 Close side seams1.35 MIN

01 / Longest station

Start with the longest station.

Read the operation IDs in the highest stack, then observe those tasks at the workstation. Check handling, quality checks and machine time as well as sewing time. A balanced chart can still describe an impossible physical layout if an operator must cross the line, change machines repeatedly or wait for material.

02 / Staffing

Separate staffing from task design.

The additional-operator answer is the difference between the feasible heuristic station count and your available crew. It is not a claim that this many hires will produce the requested quantity. Relief cover, learning, attendance, maintenance and skill availability can change the practical requirement.

03 / Capacity

Treat capacity as a ceiling.

Net minutes divided by the bottleneck cycle is a steady-state deterministic capacity ceiling for a fully staffed candidate. It excludes start-up, empty-line fill, variability, transfer delays and defects unless already embedded in the inputs.

04 / Idle and overload

Compare like with like.

Save A before changing demand or operation times. Compare the same product, allowance convention and time boundary. A higher balance percentage can accompany lower output if the bottleneck cycle lengthens. The gaps under takt are the idle; the band above it is overload.

01 / Method source, opened 30 October 2026

Takt Time · Lean Enterprise Institute

Defines takt as available time divided by demand, the denominator of this page.

TAKT 1.40S1S2S3S4S5S6S7S8OEE

On the map: the dashed takt line, net minutes divided by target.

Stations8default
Takt1.40 mindefault
Balance efficiency80.1%default
Additional operators2default

08 / Provenance: inputs and sources

Every input is illustrative; every method is sourced.

Show the register with

These are the illustrative defaults the page starts from. Choose Your inputs to see the same register with your numbers. Point at a row to see which figures it moves.

Input register: defaults, status and what to replace them with
InputValue shownStatus and basisWhat to replace it with
Net production time420 minchangedEdit ↑Illustrative. A teaching production window after excluded breaks.Replace with: Your line's planned available time, with its boundary documented.
Target output300 garmentschangedEdit ↑Illustrative. A round batch chosen to demonstrate station packing.Replace with: Demand due within the same production window.
Operation bulletin12 operations, 8.65 minchangedEdit ↑Illustrative. A simplified T-shirt route assembled for this instrument. The total is the sum of the editable SMVs.Replace with: A measured and approved operation bulletin for one product.
Available operators6 operatorschangedEdit ↑Illustrative. A deliberately short starting crew to expose a staffing gap.Replace with: Operators available to the line, excluding shared support.
RoutingRespect predecessorschangedEdit ↑Illustrative. The entered links form a simplified assembly sequence.Replace with: Engineering-approved task dependencies, checked on the actual garment.
One operator per stationFixedModel assumption. Operations cannot be split; equipment and skills are unconstrained.Replace with: a feasible machine, skill and workstation plan before implementation.

Three method sources, three programme papers in preparation.

  1. 01Takt Time ↗Lean Enterprise Institute · Publication date not stated; opened 2026-10-30

    Defines takt as available time divided by demand, the denominator of this page.

    Formula and notes

    Lean Enterprise Institute. Publication date not stated; opened 2026-10-30. Method reference only; no T-shirt timing is sourced to this publication.

    t = 420 ÷ 300 = 1.40 min

    The model stays visible.

    Takt = net minutes ÷ target garments. Largest-candidate assignment respects entered predecessors unless flexible routing is selected. Each station has one operator; tasks cannot be split. Work + idle = station count × takt + overload. Balance efficiency uses the largest station load as the cycle denominator.

    Lean Enterprise Institute, takt and operator balance; INFORMS, largest-candidate heuristic. Defaults are illustrative. ↗

    A planning aid. Not investment, legal or tax advice. Verify inputs and boundaries before an operational decision.

  2. 02Operator Balance Chart ↗Lean Enterprise Institute · Publication date not stated; opened 2026-10-30

    Defines the operator balance chart: vertical bars of work per operator against takt.

    Formula and notes

    Lean Enterprise Institute. Publication date not stated; opened 2026-10-30. Method reference only; no T-shirt timing is sourced to this publication.

    Bar = work per station; dashed line = takt 1.40 min

    Reading notes

    Do not use the illustrative route to set a worker's target. Spare operators remain outside the candidate assignment rather than being shown as if they automatically improve throughput.

  3. 03Multiobjective Line Balancing Game: Collaboration and Peer Evaluation ↗INFORMS Transactions on Education · Published online 2022-08-25; opened 2026-10-30

    Describes the largest-candidate rule used for the assignment.

    Formula and notes

    INFORMS Transactions on Education. Published online 2022-08-25; opened 2026-10-30. Method reference only; no T-shirt timing is sourced to this publication.

    Stations = 8; E = 80.1%

    Reading notes

    Equal-sized tasks keep their input order, so the result is reproducible. When the available crew cannot staff every station, this instrument withholds available-line capacity. The aggregate labour ceiling is a separate arithmetic check, not a substitute for a route. Review cycle, staffing, feasibility and work content together. The chart, assignment table, scenario URL and CSV retain enough detail for another engineer to reproduce the arithmetic.

  4. 04Utilisation Decides (wp15)GFT research programme · Not released

    Places the balance of one line inside overall equipment effectiveness.

    What it covers

    Covers OEE, line balancing and lean flow. A programme reference, not a claim of a released paper.

  5. 05Measure Before You Model (wp02)GFT research programme · Not released

    Explains why measured SMVs must come before any assignment.

    What it covers

    Covers performance measurement from the first shift. A programme reference, not a claim of a released paper.

  6. 06The Supervisor Gap (wp09)GFT research programme · Not released

    Explains why a balanced chart still needs skills on the floor.

    What it covers

    Covers skills and supervision. A programme reference, not a claim of a released paper.

09 / Close on the floor

Test the candidate on the floor.

A station plan is a hypothesis. Reconcile the operation bulletin, machine availability and skill matrix, then observe whether the work fits the same net time boundary.

Beat in a pick for each check confirmed on the floor

2 of 4 picks beaten in

Half confirmed. The remaining checks could still move the bottleneck.

Floor readiness: 2 of 4 verified

8 stations · takt 1.40 min · cycle 1.35 min · balance 80.1%

S1S2S3S4S5S6S7S8P1 ✓P2 ✓P3 ✓P4 ✓TAKT 1.40 MIN1.251.300.551.151.351.301.250.50
Warning

Do not turn an arithmetic gap into a hiring promise.

The model counts one operator per station. It excludes absenteeism, relief cover, variable performance, breakdowns, rework and transfer time unless you include them in the measured inputs. A task above takt requires a process change or a separately validated parallel arrangement.

09 / Rebalance and staff the line

Then staff the line.

2 of 4 checks confirmed: the stations settle toward the 1.40 min takt line. A target picture, not a result.

010502030406070809101112TAKT 1.40 MIN1.25S11.30S20.55S31.15S41.35S5 •1.30S61.25S70.50S8
300

Find a thread.

Type to search.