Illustrative sewing shift: availability 87.5 percent, performance 95.2 percent, quality 95.0 percent; 380 good garments.

GFT instruments / Production performance

Find the loss.
Before adding a line.

Model a sewing shift, reconcile six losses, compare scenarios and export the assumptions behind availability, performance and first-pass quality.

OEE 79.2%60 min stopped380 of 480 min good

Operate the instrumentProcedural visualisation. Schematic, not a facility.

An instrument for the decision

How much of the line's time turns into good garments?

Illustrative presets

Every preset is illustrative. No GFT programme OEE default has been supplied.

0The shift, laid straight480 min planned

  • Stopped60.0 min
  • Speed loss20.0 min
  • Rejected time20.0 min
  • Good time380.0 min
Sewing-line loss gatesThree symbolic sewing stations stand where the shift thread crosses the availability, performance and quality gates; a loop of lost minutes hangs under each. Read the adjacent figures for the calculated results.

Availability87.5%

60

Performance95.2%

20

Quality95.0%

20
First-pass good output380garments, current shift

One line. One product. One time boundary.

Three line gates with current OEE factorsAVAILABILITY87.5%PERFORMANCE95.2%QUALITY95.0%

Schematic, not a station simulation. Garment movement is qualitative; the counts and loss minutes carry the calculation. The drawing does not simulate operators, queues, work in progress, machine reliability or station-level bottlenecks.

Set the shift boundary.
min
min
sec
garments
garments
Attribute the six losses

The shift totals identify three losses only. These editable splits allocate each parent loss. Replace the illustrative equal splits with reason-coded evidence.

%
%
%

Good time / Planned time

79.2%OEE, calculated
  • Availability87.5%
  • Performance95.2%
  • Quality95.0%

87.5% × 95.2% × 95.0%

Good output at ideal rate380.0 min

Availability is the largest loss: 60.0 minutes. Review the stop log before testing a recovery action.

Illustrative worked shift

Live arithmetic, not an operating forecast. A higher score alone does not prove a better investment.

The six big losses

Every lost minute has a bucket.

Each bobbin is wound to its minutes on one shared scale, under the loop it was drawn from.

Full bobbin = 50 min, 10.4% of planned time

Availability60.0 min

Performance20.0 min

Quality20.0 min

The default allocation divides each parent loss equally between its two causes solely to demonstrate the six-loss view. Equal splits are illustrative attribution, not measured causes.

Stopped60.0 minAvailability, two bobbins
Speed loss20.0 minPerformance, two bobbins
Rejected time20.0 minQuality, two bobbins
Good time380.0 minNot a loss

60.0 + 20.0 + 20.0 + 380.0 = 480.0 min. The whole shift reconciles.

Method / Reproducible arithmetic

The time identity checks the score.

1 / 5 · Boundary

  • Planned time T480.0 min
  • Stopped, D60.0 min
  • Speed loss20.0 min
  • Rejected time20.0 min
  • Good time380.0 min

0Ledger, minutes480

T planned minutes, D downtime minutes, c ideal seconds per garment, N total garments, R first-pass rejected garments. 60.0 + 20.0 + 20.0 + 380.0 = 480.0 min. The whole shift reconciles.

  1. Step 1 / 5 · Boundary

    Start with one production boundary.

    Use a single line and a single product for the shift. Planned time includes only time when production was intended. Exclude breaks when the line was never scheduled to run. Write that convention into the supervisor's shift record before comparing days.

    Running minutes = T − D
  2. Step 2 / 5 · Stops

    Count every stop once.

    Count changeovers inside the plan as downtime. Keep minor stops inside running time when they are assigned to performance, otherwise the same stop would be counted twice. Availability is the running share of the plan.

    Availability = (T − D) / T
  3. Step 3 / 5 · Rate

    Set the rate against an ideal cycle.

    The cycle input is the ideal elapsed line cycle per completed garment, in seconds. A garment's standard minute value (SMV) measures labour content and cannot be inserted here without converting it into an effective line rate. Enter a validated line pitch, or keep the result illustrative.

    Performance = c × N / [60 × (T − D)]
  4. Step 4 / 5 · Rejects

    Take out the first-pass rejects.

    Quality is good garments over total garments. For an empty shift, undefined performance or quality factors are displayed as zero by convention. No completed garments means no good-equivalent time, and a fully stopped shift cannot also report production.

    Quality = (N − R) / N
  5. Step 5 / 5 · Reconcile

    The four parts must add back to the plan.

    The worked shift converts 480 planned minutes into 380 good-equivalent minutes: 60 stopped, plus 20 speed loss, plus 20 reject-equivalent, plus 380 good, is 480 in all. The inputs are illustrative, chosen to make the arithmetic inspectable. It is not a finding about a factory.

    OEE = A × P × Q = 380 / 480

Interpretation / Conditions

A score identifies a question to investigate.

  1. Fork
  2. Trade
  3. Not utilisation

Investigate the largest loss first.

The three parent losses are ranked in minutes. They do not infer a maintenance diagnosis: reason-coded stop events and quality records are needed to replace assumed attribution with measured evidence.

Moving minutes between stopped and running time does not move OEE.

With the good count held fixed, availability and performance move in opposite directions. A genuine recovery needs a justified change in output, quality or the production boundary.

Do not substitute utilisation for OEE.

The programme annex records CICAM capacity utilisation from 10.83 percent at CICAM 2 to 48.9 percent at CICAM 1 in a July 2023 report. This is historical context from R12, not an OEE measurement, a current operating assessment or a target for this simulator.

Tap a loop to read its question

Availability. Review the stop log before testing a recovery action. Return to the console ↑

Performance. Check small stops and line balancing against a validated ideal cycle. Open line balancing ↗

Quality. Review first-pass defects and startup rejects before accepting more output. Open inspection economics ↗

60 min

Availability 87.5% · Performance 95.2% · OEE holds at 79.2%

38.07 points apart (48.9 minus 10.83): utilisation, not OEE.

A / B decision record

Compare the change, keep the boundary.

Saved A starts as the illustrative stop-heavy preset, so the comparison can be read at once. Same planned time and ideal line cycle. Delta is current B minus saved A; allocation changes alone do not change OEE.

Set B to

59.4%OEE

A Saved scenario285 good garments, 285.0 min good time

79.2%OEE

B Current shift380 good garments, 380.0 min good time

B minus A+19.8 pp

Stopped120.0 min60.0 min
Speed loss60.0 min20.0 min
Rejected time15.0 min20.0 min
Good time285.0 min380.0 min

0Both threads on one scale480 min

Stopped: A 120.0 min · B 60.0 min · -60.0 min

Saved A compared with current B. Delta is B minus A. Point at or tab to a row to light the matching part of both rings.
MeasureSaved ACurrent BDelta
OEE59.4%79.2%+19.8 pp
Good garments285380+95
Good time (min)285.0380.0+95.0
Planned time (min)480.0480.00.0

Assumptions and sources / Status register

Defaults illustrate a method, not a benchmark.

Default shift: 60 min stopped, 400 completed, 20 rejected. Illustrative, chosen to make the arithmetic inspectable.

Every starting value, its live value, the factors it moves and its status. Point at, tab to or tap a row to lift its thread.
InputStarting valueLive valueAPQStatus
Planned time480 min480 minDoes not move qualityIllustrative
Downtime60 min60 minDoes not move qualityIllustrative
Ideal line cycle60 sec/garment60 sec/garmentDoes not move availabilityDoes not move qualityIllustrative
Total completed400 garments400 garmentsDoes not move availabilityIllustrative
First-pass rejected20 garments20 garmentsDoes not move availabilityDoes not move performanceIllustrative
Cause allocations50% each50% eachDoes not move availabilityDoes not move performanceDoes not move qualityAllocation
  • Sources. The equations follow Vorne's OEE calculation method; the cause categories follow its Six Big Losses framework. Both pages were opened for this implementation on 30 October 2026; their publication dates were not displayed. Source receipts are retained with this tool. R12 remains qualified programme-annex evidence and was not independently reverified here.
  • Sharing. Saved A is held in this page's memory. A shared link includes A and current B, and restores their inputs rather than a rounded score. CSV exports include raw inputs, unrounded outputs, units, allocation status and above-ideal diagnostics. Sharing copies a link locally; it does not submit shift records to GFT. Review a link before distributing commercially sensitive production information.
  • Limits. A planning aid. Verify inputs and boundaries before an operational decision. The model does not replace measured shift records, a validated cycle standard and engineering review.

WP02 Measure Before You Model, WP15 Utilisation Decides, WP18 Edge to Dashboard sit behind this instrument. Related papers in the research programme; publication status is controlled by the library. Research library →

Use the result in its boundary

A shift is a scenario, not a forecast.

The example does not predict a factory's performance. Replace it with measured inputs from the same line, product and time window before drawing an operating conclusion.

Minute 30 of 480 · stopped time, 60.0 min (Availability) · Which stops were unplanned breakdowns, and how long did each last?

A 59.4%B 79.2%

At B: your current shift. Turn the bezel toward A to replay the saved scenario.

The model stays visible: availability × performance × quality, with planned production time as the denominator. A planning aid. Not investment, legal or tax advice. Verify inputs and boundaries before an operational decision.

0 / 480 min120 min240 min360 min
79.2%

87.5% × 95.2% × 95.0% = 380 ÷ 480 = 79.2%