The model assumes a clean failure.
Continuous acquisition, constant traffic, constant power and a fully charged battery at the start. Real failures may hit only power, only the WAN, or different local circuits.
The combined outage envelope is deliberately explicit. Split it into separate measured cases before procurement. Cameras and allocated local network power are included; central servers, displays, cooling and site-wide loads are excluded unless you allocate them into the measured load inputs.
Simulation / what fails?
- InterfaceRUNNING
- AnalyticsSTALE
- CoreQUEUEING
- VisionRUNNING
- EdgeRUNNING
4 of 5 layers keep running. Clean: the uplink drops, mains holds.
Dirty: mains and uplink both fail with no protected supply. Qualitative design rule, illustrative.