People and power are prerequisites throughout the sequence. This gate consolidates their evidence before replication; it does not postpone safe work or electrical protection until after a productivity trial. Better Work's Ethiopia report records factory-reported improvements in line performance and absenteeism following supervisor training. The scope is a programme report from Ethiopia, not a measured outcome or a transferable effect size for Cameroon.[S40]
GFT recommends treating supervisory capability as a demonstrated operating skill. Ask the supervisor to reconcile a shift, recognise abnormal WIP, obtain quality support and manage a safe restart. Observe the deputy performing the same tasks. Classroom attendance alone should not release scale. Include operator explanations in the acceptance review: the person doing the work should understand the standard, the defect criteria and the route for raising an unsafe or infeasible instruction without losing the issue in the reporting chain.
Create a coverage map for operations whose absence could stop good throughput. Record demonstrated competence, training in progress and unavailable cover separately. Trial ordinary breaks, authorised leave and expected absence patterns through planned cover arrangements. GFT recommends funding cross-training time within the operating plan rather than assuming it occurs between full production assignments. When output depends on intensive coaching, show the coaching requirement and the expected path to independent work instead of counting the current output as settled capacity.
Ergonomic acceptance needs its own evidence. The opened Ethiopian workstation study identifies health risks and assesses discomfort in sewing work; it does not establish that a proposed workstation in Cameroon is safe. GFT recommends a local review of posture, reach, task repetition, handling and recovery, informed by operator feedback and competent assessment. A trial should retain unresolved findings and their corrective owners. A faster cycle should be rejected where it relies on an unacceptable working method.[S38]
Power evidence needs an equally explicit boundary. IFC's Cameroon diagnostic describes limited and unreliable electricity supply. This dated national assessment is a reason to measure the site, not a substitute for a local outage record. GFT recommends logging interruption start, affected operations, supply recovery, safe restart and restored accepted throughput separately. A restored socket voltage and a line producing acceptable garments are distinct events, with potentially different owners and elapsed times.[S35]
Test the response to an interruption through an approved safe procedure. Account for unfinished garments, machine settings, quality checks, data capture and material release during recovery. Utilities and maintenance leads should establish the safe operating conditions; production should demonstrate the restart routine inside those conditions. The trial should never create an unsafe outage merely to complete a checklist. Where a physical test is inappropriate, document the limitation and use a reviewed simulation until an authorised test becomes possible.
The scale gate should combine skill cover, attendance stability, reasonable working arrangements, closed ergonomic findings and measured power recovery. Thresholds belong to the specific operation and must be set before acceptance. If cover remains unavailable, restrict the scope or schedule rather than claim capacity that assumes permanent exceptional effort. If power performance is unresolved, retain a conditional capacity range and fund the measurement needed to narrow it. These recommendations require local safety and labour review where applicable; they are not legal advice.
Assign these supporting actions when the first pilot budget is prepared. The workforce lead should identify paid learning time and accessible reporting routes; the utilities lead should identify the permitted recovery procedure and competent support. Their evidence may mature alongside the production trial, but the sponsor should not release an operating scope whose essential support has neither an owner nor an authorised resource allocation.