Research librarySeeing Every Defect

Chapter 14 of 14 · Part IV · Draft web edition

A four-phase crawl-walk-run roadmap deploys computer vision in step with factory ramp and proves payback inside the PMS

Synchronising vision deployment with the eighteen-month Performance-Management System rollout takes a greenfield line from manual logs to closed-loop quality without operational shock.

Sections
7
Exhibits
5
Minutes
26
Sources
17
EX 63 · P2: Roll maps and model tuning: from 9 to 15 (illustrative months from programme approval)

The cloth is woven from this chapter's 5 exhibits: each weft is one exhibit's own data, normalised; each warp group is a section. The probe reads the exhibit's own value where it crosses. Procedural visualisation, not a measurement.

The chapter as a draft: 7 sections, 3 exhibit wefts, one shuttle.

Lead exhibit · 63ScheduleillustrativeFour conditional phases sequence inspection capability with factory and PMS maturity
05101520P0: Baseline and acceptanceP1: Fabric and garment triageP1: Audit and corrective actionP2: Roll maps and model tuningP2: Conditional line replicationP3: Seam and traceability links

Read-outP0: Baseline and acceptance: from 0 to 3 (illustrative months from programme approval)

Method and source

Illustrative GFT deployment plan, not a record of implementation. Phase 0 prepares the measurement system and acceptance evidence; Phase 1 stabilises two inspection boundaries; Phase 2 adds cutting feedback and local model adaptation; Phase 3 adds selected inline seams and traceability. Every transition depends on evidence, not elapsed time alone.

Unit: illustrative months from programme approval. Status: illustrative. Sources: R27, R29, R31, S04, S07, S19. Illustrative figures are teaching examples, not measured factory results.

The chapter's warpBar: share of the reading · square: an exhibit

Section 14.0 · Opening · 1 min · no exhibit of its own · one movement Go to section ↓

Overture · 1 min

A greenfield garment factory should release computer vision through four condition-gated phases, not through a single automation purchase. The illustrative roadmap runs for 24 months. Phase 0, Months 1 to 3, establishes the manual Quality Log, representative test sets and vendor acceptance. Phase 1, Months 4 to 9, stabilises incoming-fabric and finished-garment inspection with human review. Phase 2, Months 10 to 15, connects verified roll maps to cutting and tunes models on local evidence. Phase 3, Months 16 to 24, adds critical-seam inspection and traceability links after the earlier stations have proved their operating value.[R29][S04][S07][S19]

¶ 01 · 4 sources

The illustrative roadmap runs for 24 monthsillustrative

R29S04S07S19

The answer is therefore crawl, walk, run, with a gate at every change in scope. A calendar date may trigger a review, but it cannot authorise the next expenditure. The Performance-Management System (PMS) must show stable denominators, acceptable defect escapes, manageable false alarms, completed corrective actions and reconciled savings before the factory adds cameras or model classes. This chapter is a proposed deployment and value-realisation method, not a report of an installed GFT system or a guaranteed investment return. Nothing here constitutes investment, legal or tax advice.

¶ 02

14.12 min · 5 paragraphs · 1 exhibit

One gated roadmap aligns the factory ramp, the PMS and digital adoption

GFT's Cameroon textile programme places feasibility, performance management and digital strategy on one phase spine. That design matters because each workstream removes a different constraint. Feasibility defines the operating boundary and capital sequence. The PMS defines the measures, responsibilities and review cadence. The digital strategy supplies tools only when their inputs and decision rights exist. A camera installed before those three elements agree would create a technical station without an operating purpose.[R27][R29]

The sequence also respects data dependency. Pre-trained and one-class vision can begin with images of current production rather than a sales ledger. PatchCore explicitly addresses the cold-start problem by fitting a model with nominal images only. Demand forecasting occupies a different position: the programme defers local forecasting until useful sales history exists, even though fashion-sector research reports substantial potential gains from artificial intelligence at scale. Generative design remains a later partner-led capability rather than a prerequisite for inspection.[R27][R29][R31][S04]

¶ 02 · 4 sources

R27R29R31S04

Exhibit 63 makes the proposed timing inspectable. Its bars are planning allocations, not commitments or achieved milestones. The phases overlap because preparation, operation and review must continue together. Manual logging does not stop when the first camera arrives, and vendor acceptance does not end when a model is fine-tuned.

The ramp changes the economics as well as the hardware count. During early production, a station may have too little volume to recover its fixed cost. During later expansion, an unproven station can multiply false alarms and review queues across several lines. The inherited record of CICAM utilisation between 10.83 and 48.9 percent in July 2023 is a warning about underused industrial capacity, not a benchmark that a new vision facility will reproduce. Capital release must therefore follow measured throughput and quality at the actual ramp, not nameplate output.[R12]

¶ 04 · 1 source

R12

Three review rhythms keep the phase spine coherent. The line review protects current production and approves containment. The weekly plant review examines measurement quality, recurring causes and maintenance. The monthly investment review compares verified value with the next phase's full cost. Each review receives the same event identifiers and definitions, so an engineering improvement cannot appear as a financial gain while the production record shows unresolved losses.

¶ 05

14.23 min · 1 sub-steps · read with a related exhibit

Phase 0 proves the measurement system before approving the vision station

Related · chapter 029 paragraphs step it

Related exhibit 05 · chapter 02TrajectoryillustrativeContinuous inspection loses capture while task rotation interrupts the decline
6080100Start15 min30 min60 min90 min120 min

Read-outStart: Continuous manual block 70, Manual with 30-minute task rotation 70, Vision reference above 90 percent 91 (illustrative percent of true defects captured)

Method and source

Illustrative scenario, not observed factory data. Continuous manual capture starts at 70 percent, within the inherited 60 to 70 percent range (R29), then declines over two hours. The rotation series resets after each 30-minute task change to test Sandia's recommended maximum continuous inspection block (S0205). Textile evidence also reports difficulty sustaining focus beyond ten minutes (S03). The 91 percent vision reference represents the inherited above-90-percent benchmark, not a measurement or guaranteed local result (R29).

Unit: illustrative percent of true defects captured. Status: illustrative. Sources: R29, S03, S0205. Illustrative figures are teaching examples, not measured factory results.

Read this exhibit in its chapter ↗
14.2 · Introduction · paragraph 1 of 9

Phase 0 begins with a manual record that can survive automation. The proposed Quality Log captures units inspected, defect count, defect class, severity, roll or bundle, station, style, disposition and verifier. The defect dictionary proposed for this paper contains 42 classes, but a code is useful only when two reviewers apply it to the same physical condition in the same way. Training must therefore use real specimens, borderline cases and explicit severity rules, not merely a list of names.[R29]

The manual baseline needs a defined opportunity and denominator. Fabric inspection may use linear metres, rolls or garment-equivalent panels. Garment inspection may use units, seams or defects per hundred units. These measures should not be merged into one percentage. A baseline also needs a time window and product context: fabric construction, colour, print, style, line, shift and inspector can all alter the difficulty of detection. Without those fields, a later improvement may reflect an easier production mix rather than a better inspection system.

An independent reference sample tests the manual record before it becomes the comparator. A quality lead and a second qualified reviewer independently grade a representative set, resolve disagreements and retain the reasons. The factory then measures agreement by class and severity. This does not make the reference infallible. It creates an auditable basis for estimating false negatives, false positives and pending decisions. The inherited 60 to 70 percent manual-inspection range is context for that test, not a substitute for factory-specific measurement.[R29]

14.3 Representative local specimens decide vendor acceptance

The acceptance set should cover the materials and defect opportunities the factory actually expects. Incoming trials can include traceable cotton cloth associated with the northern supply base, while recognising that SODECOTON's inherited profile of more than 220,000 producers and nine ginning plants says nothing about the quality of any particular roll. Each specimen still needs its own supplier, lot, construction and condition record.[R03]

A useful trial separates the set used to configure the station from the set used to accept it. The first supports lighting, focus, thresholds and model selection. The second remains untouched until the formal run. It includes nominal production, rare but consequential defects, difficult colours and prints, and samples close to the acceptance boundary. The factory should report class-level recall and precision, review burden per inspected length or unit, and the number of unreviewed cases. One aggregate accuracy figure would hide the errors that determine safety and workload.

The edge-cascade study shows why this granularity matters. On its disjoint 249-image benchmark, a recall-prioritised first stage found all 20 defective images but also flagged 113 of 229 non-defective images. Its authors report that 85 percent of forwarded frames were false alarms and position the system as assisted triage rather than autonomous acceptance. Those results come from four knit-fabric classes and one small benchmark, not a Cameroonian factory. They nevertheless demonstrate why a perfect recall headline can still produce an unworkable review queue.[S07]

Optical and timing tests belong in the same acceptance protocol. A line-scan study demonstrates high-speed acquisition, triggering, illumination and preprocessing in a PCB application, which supports the engineering method but does not establish textile-defect performance. The fabric station must therefore prove resolution, encoder synchronisation, contrast and processing time on its own moving web. The inherited reference of up to 60 metres a minute is an upper contextual benchmark, not a default factory requirement.[R29][S14]

Finally, the setup phase tests failure recovery before purchase. The station disconnects from the network, loses and regains power under the approved protection arrangement, and restores its local event buffer without duplicate records. The buyer also verifies export of images, labels, model identifiers and quality events in documented formats. Data ownership, offline inference and an exit path are acceptance criteria, not contractual afterthoughts.

14.43 min · 1 sub-steps · read with a related exhibit

Phase 1 stabilises two inspection boundaries through human triage

Related · chapter 069 paragraphs step it

Related exhibit 27 · chapter 06Bar chartsourcedUnsupervised and self-supervised models exceed 89 to 99 percent anomaly detection without labelled defect history
025507510065Manualbaseline…89.5Gabor-CAE(recall)99.6PatchCore(AUROC)99.6SimpleNet(AUROC)99.9GLASS(AUROC)70.3RegLossMVTec (P…67.7RegLossGreige (…

Read-outManual baseline (acc.): 65 percent benchmark score (AUROC, recall or pixel AP)

Method and source

Compares published metrics: manual visual inspection baseline midpoint (65.0 percent from 60 to 70 percent range, R29); Gabor-CAE recall on Standard Fabric Defect Glossary with zero false alarms (89.5 percent, S06); PatchCore AUROC on MVTec AD (99.6 percent, S04); SimpleNet AUROC on MVTec AD (99.6 percent, S0605); GLASS AUROC on MVTec AD (99.9 percent, S13); and RegLoss pixel-level AP on MVTec AD (70.3 percent) and plain grey fabric (67.7 percent, S0601).

Unit: percent benchmark score (AUROC, recall or pixel AP). Status: sourced. Sources: R29, S04, S06, S13, S0601, S0605.

Read this exhibit in its chapter ↗
14.4 · Introduction · paragraph 1 of 9

In the illustrative roadmap, Phase 1 starts where a detection can prevent a different downstream decision. At fabric entry, the decision is whether to accept, query, splice or map a roll before cutting. At final garment inspection, the decision is whether to pack, repair, downgrade or hold an item. These boundaries have different images, denominators and failure costs. They should be commissioned as two operating stations with a shared event schema, not as two installations of the same generic model.

The fabric station runs in shadow mode before it influences material disposition. The team compares its output with the manual perch and the independent reference sample, then investigates disagreement by defect class and fabric context. A missed hole has a different consequence from an over-flagged cosmetic variation. The operating threshold must reflect that asymmetry while keeping the human review queue within the available inspection capacity. Once the station enters assisted operation, severe or ambiguous cases still require an authorised disposition.

Cold-start models help during this stage, but their benchmark language must remain precise. PatchCore reports image-level anomaly detection AUROC of up to 99.6 percent on MVTec AD, alongside the ability to learn from nominal examples. AUROC on that benchmark is not equivalent to defect recall on Cameroonian cotton, nor does a nominal memory bank remove the need for an acceptance set. The practical benefit is a starting mechanism for unfamiliar fabric; the factory still has to choose and validate its operating threshold.[S04]

The finished-garment study provides a different and equally bounded reference. Its Addis Ababa dataset contains 1,000 trouser images. The reported system achieved 86.7 percent overall accuracy and processed a sample in 0.45 seconds, while class results ranged from 80.0 percent for seam slippage to 96.7 percent for untrimmed threads. Those findings support a cycle-time and workflow hypothesis. They do not justify autonomous release or a universal accuracy target for every garment style.[S19]

Human triage joins these stations to the PMS. In the metal-textile workflow described by Elsen and co-authors, the model handles clear pass cases and sends doubtful cases to a human inspector. The garment adaptation is to route clearly acceptable frames under an approved rule, route anomalies and low-confidence decisions to review, and record the verifier's conclusion alongside the model output. This structure creates useful labels while preserving human responsibility for consequential dispositions.[S34]

14.5 A manageable exception queue is an acceptance result

The daily station review tracks more than detections. It records inspected volume, auto-passed volume, flagged volume, verified defects, rejected alarms, pending cases and downstream escapes. These quantities reveal whether the station is operating within its design. A rising pending count can indicate insufficient review capacity. A rising false-alarm count can indicate lint, lighting drift, a new fabric or a threshold problem. A falling defect count accompanied by rising customer escapes can indicate dangerous under-detection rather than improvement.

The edge study's measured throughput also deserves careful interpretation. Its parallel pipeline reached 13.45 frames a second against 9.86 frames a second for a sequential detector loop, but the authors attribute 91 percent of the speed gain to overlapping JPEG decode with inference rather than to the cascade itself. A factory acceptance test should therefore measure the complete data path, including acquisition, decode, inference, display and event writing. Model latency alone cannot prove line capability.[S07]

Corrective action begins during Phase 1, not after model tuning. Statistical Quality Control and Failure Mode and Effect Analysis provide a disciplined route from verified defect patterns to containment and investigation. The Indonesian garment case used p-charts and risk priorities to identify an incompletely controlled print process. The transferable lesson is to connect the signal to a reaction plan, not to transfer its defect rates or risk scores.[S26]

The launch phase can close only when the operating record is complete enough to support comparison. Representative production runs have known denominators, unresolved critical cases are contained, the review queue is staffed, and downstream audits reconcile with station decisions. The team must also demonstrate that a supervisor can open an exception, assign an action and verify closure without re-keying the event. If those conditions fail, the remedy is to stabilise the station, not to add more stations.

Key figures from chapter 11 · Exhibit 50Key figuressourcedGarment studies support integrated control rather than isolated detection
  • 0.3Digital quality controlPath coefficient; reported p = 0.002 in S24
  • 0.6Production automationPath coefficient; reported p = 0.000 in S24
  • 64.5%Quality variance explainedJoint result for both predictors in S24
  • 23%Two dominant jacket defectsBroken threads and puckering among 16 types in S25
  • 107 / 1,380Defective T-shirtsObserved units in the S26 case

Read-outDigital quality control: 0.3. Path coefficient; reported p = 0.002 in S24

Method and source

S24 reports SEM-PLS associations in one Indonesian garment company. S25 reports the share of two dominant categories among 16 jacket defect types. S26 reports defective printed T-shirts in another case. These results are not Cameroonian benchmarks or GFT operating outcomes.

Unit: reported study results. Status: sourced. Sources: S24, S25, S26.

Read this exhibit in its chapter ↗

14.63 min · 1 sub-steps · read with a related exhibit

Phase 2 converts verified detections into cutting decisions and local model evidence

In the illustrative roadmap, Phase 2 begins only after Phase 1 has produced a usable record of local operating conditions. Its first purpose is to improve material yield. A roll detection carries cross-web and along-web coordinates against a roll identifier. Spreading and cutting then transform that roll into plies, panels and bundles. Each transformation needs a linked identifier and an explicit record of splices, end loss and marker movement. Without that genealogy, an accurate roll coordinate cannot reliably locate a cut panel.

¶ 01

Phase 2 begins only after Phase 1 has produced a usable record of local operating conditionsillustrative

Related · Exhibit 31 · chapter 06

The cutting lead approves the disposition rules during early operation. A severe fault may require removal. A minor fault may be acceptable outside a visible panel zone. A questionable mapping may require physical verification rather than automatic nesting. These rules protect two forms of value at once: they avoid sewing known defects into garments, and they avoid discarding usable cloth through excessive caution. The PMS records the resulting recut, splice, downgrade or accepted use so that material savings can be reconciled rather than inferred from model detections.

¶ 02

14.7 Local adaptation follows a controlled comparison

14.7

The second purpose of the scale phase is to reduce avoidable review work and improve class-specific detection on local materials. In this illustrative design, verified crops from Phase 1 become training and validation candidates, but they require deduplication, label review and separation by roll, lot or production run. Nearby frames from one defect must not leak into both training and test sets. Rare critical classes should remain visible in evaluation even when that makes the reported result less flattering.

¶ 03

verified crops from Phase 1 become training and validation candidatesillustrative

The outline's planning milestone of 10,000 verified local crops is illustrative, not a statistical guarantee of readiness. A smaller, well-represented and independently reviewed set may be more useful than a larger collection of repetitive or inconsistent labels. The release decision should depend on class coverage, label quality, the proposed operating threshold and performance on a held-out production period. Every new model version also needs a rollback path and a record of the data and configuration that produced it.

¶ 04

The outline’s planning milestone of 10,000 verified local crops is illustrativeillustrative

Patterned fabrics require particular caution. The reverse-distillation fabric study addresses diverse colours, textures and defect types across MVTec AD, AITEX, TILDA and a textile-facility dataset. That breadth supports testing distillation as a candidate for domain variation, not assuming that one nominal model will cover every print. A new motif or dye lot should trigger a defined review and, where necessary, re-enrolment before the station returns to routine operation.[S12]

¶ 05 · 1 source

S12

A candidate model should run beside the incumbent on comparable production before replacement. The review compares critical-class recall, false alarms per inspected unit or length, pending volume, processing time and downstream escapes. It also examines whether the proposed gain persists across lines, shifts and material lots. A model that improves the aggregate score while weakening a critical class does not pass. Approval covers a named version at a named threshold, not an indefinite permission to update weights.

¶ 06

Phase 2 is also the earliest sensible point for local demand forecasting in the programme sequence, because the factory now has some sales and order history. The fashion-sector figures in the shared register describe potential from artificial intelligence at scale, not a guaranteed result for this plant. Forecasting should remain a separate acceptance exercise with its own baseline and error measures. It must not borrow credibility from the vision station or divert attention from unresolved quality losses.[R27]

¶ 07 · 1 source

R27

Replication follows the same evidence rule as model updates. A second line receives the proven station design only after its own lighting, mechanics, product mix and reference sample have been checked. The original station's event schema and reaction plan can transfer. Its thresholds and performance cannot be assumed to transfer without verification.

¶ 08

14.82 min · 5 paragraphs · read with a related exhibit

Phase 3 adds critical-seam control and traceability without destabilising the line

In the illustrative roadmap, Phase 3 addresses defects created between the cut bundle and the finished garment. The factory selects critical seams from verified Pareto evidence, buyer requirements and failure severity. It does not place a camera at every needle by default. A station earns its position when earlier detection can contain a suspect bundle, guide a needle or tension check, and prevent repeated rework without creating an unmanageable stop pattern.

¶ 01

Phase 3 addresses defects created between the cut bundle and the finished garmentillustrative

Related · Exhibit 04 · chapter 01

The sewing-model evidence supports a measured trial rather than a broad autonomy claim. In one study, adding Coordinate Attention to the authors' YOLOv8 configuration increased mAP@0.5 by 3.7 percentage points. The complete improved configuration also reduced speed from 48 to 43 frames a second on the reported experimental setup. Its authors acknowledge limited generalisation to complex textured backgrounds. A Cameroonian acceptance run must therefore test both detection and production consequences on its own garments.[S17]

¶ 02 · 1 source

S17

Inline reactions should be proportional to risk. A critical seam failure can require immediate containment. Repeated minor faults may justify a run-rule, a supervisor review or a maintenance check rather than an automatic stop. Every intervention records stopped time, affected bundles and the subsequent verified result. This prevents the quality dashboard from claiming a gain while the production record hides lost availability.

¶ 03

Traceability integration follows the same condition gate. Research on Digital Product Passport readiness describes fragmented upstream data, limited digital systems and methodological complexity as barriers for garment manufacturers. It also notes that textile-specific requirements continue to be defined through later acts and product rules. Phase 3 should therefore make quality and material records exportable and traceable, without claiming that a particular passport format is already sufficient for future compliance.[S27]

¶ 04 · 1 source

Phase 3 should therefore make quality and material records exportable and traceableS27

S27

Partner-led design experiments may begin only after the production data spine is stable. The shared register describes multi-model pipelines spanning fabric construction, shade, weave and silhouette, but those capabilities do not repair an unreliable inspection record. They remain a separate Tier 3 pilot with their own acceptance criteria. The run phase is complete when added digital scope no longer degrades containment, review workload or data integrity.[R31]

¶ 05 · 1 source

R31

14.92 min · 6 paragraphs · 2 exhibits

Condition gates and paired controls decide whether the programme advances

Exhibit 64 converts the roadmap into an evidence contract. The thresholds are deliberately expressed as approved local criteria rather than universal numbers. Before each trial, the sponsor, production lead and quality lead must convert them into measurable values suitable for the product and buyer. They must also state who signs the gate and what evidence would block it.

Exhibit 64RegisterillustrativeEach phase releases capital only after operational and economic evidence agrees
Gate
P0 to P1
Required evidence
Stable manual schema; sealed local acceptance; offline recovery
Capital or scope released
Two assisted inspection boundaries
Hold condition
Unresolved labels, optics or export failure

Read-outGate: P0 to P1. Required evidence: Stable manual schema; sealed local acceptance; offline recovery. Capital or scope released: Two assisted inspection boundaries. Hold condition: Unresolved labels, optics or export failure

Open the full register (4 rows)
P0 to P1Stable manual schema; sealed local acceptance; offline recoveryTwo assisted inspection boundariesUnresolved labels, optics or export failure
P1 to P2Complete denominators; controlled escapes; staffed review; closed actionsRoll-to-marker link and candidate model tuningPending critical cases or unreconciled downstream audits
P2 to P3Matched-run model gain; conserved roll genealogy; verified material valueSelected critical seams and further linesCritical-class regression or broken coordinate mapping
P3 to runStable added stations; traceable exports; cumulative cash reconciliationRoutine operation and controlled renewalRising stops, incomplete records or unverified savings
Method and source

Illustrative governance design. Cited studies support inspection, triage and management mechanisms, not these exact gates. Local owners must set numeric acceptance limits before each trial and retain the signed evidence.

Unit: illustrative GFT phase-gate contract. Status: illustrative. Sources: R29, S04, S07, S19, S24, S26. Illustrative figures are teaching examples, not measured factory results.

The gate is not a claim that management integration guarantees quality. In the Central Java garment study, digital quality control and production automation jointly explained 64.5 percent of product-quality variance through a survey-based structural model. That association supports combining technology with management routines, but it does not provide a causal effect or a phase threshold for another factory. Local gate evidence remains necessary.[S24]

¶ 01 · 1 source

S24

Exhibit 65 positions the main deployment risks on two illustrative scales. The coordinates are workshop planning scores, not observed frequencies. Their purpose is to pair every material risk with an engineering control and a management owner before capital is released.

Exhibit 65Decision mapillustrativeSix deployment risks require both a technical control and a management response
Prepare contingencyPriority controlsMonitor routinelyReduce recurring frictionPerceived likelihood without control →Perceived effect on quality and payback →Lint and optical foul…Power or storage inte…False-alarm overloadPrint or dye-lot driftInspector bypassVendor lock-in

Read-outLint and optical fouling: Perceived likelihood without control 8, Perceived effect on quality and payback 7. Quadrant: Priority controls

Method and source

Illustrative workshop scores, not measured likelihoods or severities. Higher x means greater perceived operational likelihood without controls; higher y means greater perceived effect on quality and payback. Teams must rescore with local FMEA evidence.

Unit: illustrative score from 0 to 10. Status: illustrative. Sources: S07, S12, S26, S34. Illustrative figures are teaching examples, not measured factory results.

Lint and optical fouling require protected housings, cleaning standard work and image-quality checks. Power and storage interruption require conditioned power, clean shutdown, durable local event identifiers and duplicate-free recovery. Print or dye-lot drift requires a reference check, controlled re-enrolment and a route back to the prior approved configuration. These are station-level controls, but the PMS must record completion and exceptions if they are to remain effective.

¶ 01

False-alarm overload requires class-specific threshold review and enough verifier capacity. Inspector bypass requires usable screens, training, measured agreement and a response policy that does not punish honest escalation. Vendor lock-in requires portable data, documented export, local inference and contractual exit rights. The SQC and FMEA method is useful here because it links risk priority to concrete work standards and equipment checks rather than leaving risk as a colour on a matrix.[S26]

¶ 02 · 1 source

S26

Every gate also needs explicit stop conditions. A critical defect escape, a broken roll-to-bundle chain, a rising unreviewed queue, unexplained denominator loss or an irreconcilable savings claim should hold expansion. The response may be to return to shadow mode, restore the previous model, retrain staff or repair the measurement system. A phase gate is credible only when the factory is willing to use it.

¶ 03

14.104 min · 8 paragraphs · 2 exhibits

The PMS proves payback only when physical and financial records reconcile

Step 1 of 6Opening

Exhibit 67 · illustrativeMaterial avoidance, not inspection labour, carries the illustrative monthly value case

0250,000500,000750,0001,000,0000Opening+600,000Fabricconversion av…+30,440Rework labouravoided+360,000Seconds lossavoided−150,000Incrementaloperating cost840,440Net monthlyvalue0500,0001,000,000Opening0Fabric…+600,000Rework labour…+30,440Seconds loss…+360,000Incremental…−150,000Net monthly value840,440

Opening

Opening: total 0. Running total 0 XAF per representative stable month · illustrative

The value-realisation scorecard begins with external reference points, then replaces them with local measurements.

Fabric conversion avoided

Fabric conversion avoided: adds 600,000. Running total 600,000 XAF per representative stable month · illustrative

Rework labour avoided

Rework labour avoided: adds 30,440. Running total 630,440 XAF per representative stable month · illustrative

Seconds loss avoided

Seconds loss avoided: adds 360,000. Running total 990,440 XAF per representative stable month · illustrative

Incremental operating cost

Incremental operating cost: removes 150,000. Running total 840,440 XAF per representative stable month · illustrative

Net monthly value

Net monthly value: total 840,440. Running total 840,440 XAF per representative stable month · illustrative

The method behind it: Method.

Method and source · Exhibit 67

Illustrative arithmetic from the worked example, not observed factory value. Additional fabric interceptions: 100,000 x 0.02 x (0.90 - 0.65) = 500; x XAF 1,200 = XAF 600,000. Rework: 600 x 12 / 60 = 120 hours; x XAF 253.667 = XAF 30,440. Seconds: 400 x XAF 900 = XAF 360,000. Net = 600,000 + 30,440 + 360,000 - 150,000 = XAF 840,440. Simple payback on illustrative XAF 12,000,000 capital = 14.3 months.

Unit: XAF per representative stable month. Status: illustrative. Sources: R14, R16, R29. Illustrative figures are teaching examples, not measured factory results.

14.10 · the bodyExhibit 67 above; its figures are illustrative where marked.

The value-realisation scorecard begins with external reference points, then replaces them with local measurements. Exhibit 66 keeps the cited benchmarks visible without presenting them as GFT results. Their scopes differ: classification accuracy, web speed, frame throughput and return estimates cannot be combined into one performance score.

The internal scorecard has five linked tests. Detection performance measures verified false negatives and false positives by class. Flow performance measures Right First Time, Defects Per Hundred Units, pending volume and review time. Material performance measures fabric accepted, spliced, recut, downgraded and scrapped under a conserved balance. Workforce performance measures agreement, training and action closure. Financial performance measures realised savings and the full cost of owning and operating each station.

¶ 02

Attribution requires a baseline and a counterfactual. The team compares equivalent products and operating conditions, retains changes in style and material mix, and distinguishes the effect of the camera from maintenance, training or supplier action. Where several interventions occur together, the review should report the combined effect rather than assign the same saving to each intervention. Detection counts alone are not benefits.

¶ 03

The worked example also explains the reporting sequence. First, the Quality Log verifies the additional interception and the garment disposition. Next, the material and line records prove that the physical loss did not occur elsewhere. Finance then approves the unit value and operating cost. Finally, the investment review updates cumulative cash using actual ramp output. A stable-rate calculation can screen a proposal, but only the cumulative record can declare capital recovered.

¶ 04

The Ethiopian garment study's 12 to 18 month return estimate provides a useful comparison for the illustrative 14.3-month result, not independent confirmation. Geography, product, defect prevalence, equipment scope and cost assumptions differ. The correct conclusion is narrower: a phased vision programme can test payback inside the PMS, and the test is credible only when physical reconciliation and full operating cost remain visible.[S19]

¶ 05 · 1 source

The Ethiopian garment study’s 12 to 18 month return estimate provides a useful comparison…illustrative

S19

GFT's final recommendation is to fund the next phase from evidence produced by the current one. Start with a trustworthy manual record. Stabilise two high-decision-value inspection boundaries. Add cutting feedback and model adaptation after verified local data exist. Add inline seams and traceability only when the factory can absorb them. Throughout, keep production as the warp and measurement as the weft, so every expansion carries its own proof of quality and value.

¶ 06

Check the record

The chapter keeps its sources within reach.

Every knot is a source this chapter cites; select one to read its record, or filter the register by grade. Publication dates and inherited-source limits stay explicit. Read the paper's full evidence summary.

17 sources · 50 citation marks on this pageMost cited: R29, 8 times

Grade AGrade BGrade CKnot size: citations on this page

All 17 records shown

R03 · Grade C · inherited record

SODECOTON

Inherited evidence R03

Company profile: more than 220,000 cotton producers supported in northern Cameroon; nine ginning plants; two oil mills.

Publication date unrecorded. Inherited source-text record. The original publication has not been independently reopened for this web edition.

Chapter source notes

R29 MDPI; industry inspection literature. Publication date unrecorded; inherited source-text check.

S04 arXiv / IEEE CVPR. 2021-06-15.

S07 arXiv. 2026-08-12.

S19 Textile Research Journal. 2026-09-06.

R27 McKinsey, The State of Fashion 2025. Publication date unrecorded; inherited source-text check.

R31 arXiv 2509.04705. Publication date unrecorded; inherited source-text check.

R12 Business in Cameroon. Publication date unrecorded; inherited source-text check.

R03 SODECOTON. Publication date unrecorded; inherited source-text check.

S14 Applied Sciences (MDPI). 2024-12-23.

S34 IntechOpen. 2025-01-03.

S26 Jurnal Teknik Industri (JATRI). 2026-09-25.

S12 arXiv. 2024-01-04.

S17 Journal of Measurements in Engineering. 2024-09-09.

S27 Sustainability (MDPI). 2026-07-13.

S24 CEMERLANG: Jurnal Manajemen dan Ekonomi Bisnis. 2026-08-03.

R14 WageIndicator. Publication date unrecorded; inherited source-text check.

R16 WageIndicator. Publication date unrecorded; inherited source-text check.

Keep the thread · chapter 14 of 14

The argument closes on this chapter.

Move the shuttle along the rack to preview any chapter: its sections, exhibits and reading time. Draft web edition. This research is not investment, legal or tax advice; illustrative models are not measured factory results.

The paper's rack · 14 boltsBolt length: reading time

14Part IV: Workforce Transition, Traceability Governance and the Phased Deployment Roadmap

A four-phase crawl-walk-run roadmap deploys computer vision in step with factory ramp and proves payback inside the PMS

Synchronising vision deployment with the eighteen-month Performance-Management System rollout takes a greenfield line from manual logs to closed-loop quality without operational shock.

  • 14.1One gated roadmap aligns the factory ramp, the PMS and digital adoption
  • 14.2Phase 0 proves the measurement system before approving the vision station
  • 14.4Phase 1 stabilises two inspection boundaries through human triage
  • 14.6Phase 2 converts verified detections into cutting decisions and local model evidence
Reading time
26 min
Exhibits
5
Sections
7
Return to the opening
← Previous: chapter 13, Every defect frame logged at the edge builds an auditable quality and waste ledger for Digital Product PassportsContinue the threadChapter 14 · A four-phase crawl-walk-run roadmap deploys computer vision in step with factory ramp and proves payback inside the PMS